Click on the number in the active or completed column to see the list of projects and percent completed for each business case. Table updated: October 2016. The next update is anticipated to occur in January 2017.
Business Case | Active Projects | Completed Projects | Total Projects |
---|---|---|---|
Budgeting Process | 3 | 0 | 3 |
Shared Service Centers | 0 | 2 | 2 |
Construction | 0 | 3 | 3 |
Enrollment Management - Domestic | 0 | 4 | 4 |
Enrollment Management - International | 0 | 4 | 4 |
Facilities | 0 | 4 | 4 |
Human Resources | 1 | 3 | 4 |
Libraries | 0 | 4 | 4 |
Procurement & Sourcing | 0 | 5 | 5 |
Research Administration | 1 | 2 | 3 |
Information Technology | 0 | 11 | 11 |