May 24, 2013

Friday, May 24, 2013

Hiring and Recruiting: streamline processes and increase HR workflow implementation

  • Activities & Accomplishments
    • Configuration activities for phase I completed.
    • Began user-acceptance testing (UAT), to include ROC and HR Recruitment staff.
    • Met with the majority of the deans about recruitment and other CFE projects.
  • Issues
    • Need a few more days beyond June 1 for system to go-live.
  • Activities Planned
    • Finish UAT and finalize implementation and communication details.
    • Define statement of work for phase II of project.

Job Descriptions: standardize descriptions and create KUL/KUEC salary bands

  • Activities & Accomplishments
    • Met with leadership, HR staff, and small work group to review details of CBIZ recommended classification structure.
  • Issues
    • Review of classification structure difficult minus clear title definitions from CBIZ.
  • Activities Planned
    • Formulation of implementation plans.
    • Progress report to campus.

Performance Management: redesign and implement improved processes

  • Activities & Accomplishments
    • Viewed demo of Kenexa PM/LM systems.
    • Determined that RFP should be reopened for vendor bidding.
  • Issues
    • Need to determine if PM/LM implemented first.
  • Activities Planned
    • Develop RFP.


Changing for Excellence Feedback
KU Today
Changing for Excellence News

NACUBO Cover

Changing for Excellence was the featured cover story in the January, 2015 edition of Business Officer, the official magazine of the National Association of College and University Business Officers (NACUBO). You can read the full story online.

One of 34 U.S. public institutions in the prestigious Association of American Universities
44 nationally ranked graduate programs.
—U.S. News & World Report
Top 50 nationwide for size of library collection.
—ALA
5th nationwide for service to veterans —"Best for Vets: Colleges," Military Times